1/17/22:

Most of the siding is on. Will be painted in a while. David Zenner and GMUUC construction oversight team met with MP to discuss adjustments. All is going well.

12/4/21: 

Framers are working today and plan on having roof done. Good news since rain coming in tomorrow. ROOF NOT FINISHED.

First two photos are from Morrison Moore Parkway. Third is the back of the building and last is admin side from Owens Rd.

12/3/21:

1. AEMC finally has electricity to our building site. No need for gas run generator.

2. The septic tank is in.

3 - 5. Long distance view and then closer. By the end of the day we should have plywood around most of the building. The administration wing has plywood on the roof.